Tuesday, June 18, 2013

June 2013 Construction Updates

Gymnasium
  • Gymnasium floor is finished. 
  • Bleacher install to start the week of June 24th 
Weight/Wrestling Rooms
  • Painting is near complete.
  • Ceiling grid is complete at weight room.
FEMA Safe Room
  • Mechanical/Electrical/Plumbing rough in is near complete.
  • EIFS ceilings are complete in all shower areas.
  • Walls are painted
  • Cabinets are installed.
  • Lockers are installed.
  • Ceramic Tile is complete.

Music Rooms
  • Cabinet installation is near complete.
Kitchen
  • Existing equipment has been moved and installation is in progress.
Auditorium
  • Concrete floors, steps, and risers are complete.
  • Painting is 80% complete.
  • Drywall clouds are 100% framed and hung.
  • Drywall clouds are 80% taped and finished.
  • Rough in is complete.
  • Speakers have been installed.
Sr. High School Wing
  • High School wing has been punched out.
  • Punch-list items are being worked on.
Industrial Education Wing
  • Mechanical rough in is in progress.
  • Auto and metal shop walls are primed
  • Dust collection system in being installed
  • Electrical rough in is in progress.
Science, Art, Special Education, ETC
  • Terrazzo is ground
  • Mechanical/electrical trim out is in progress.
  • Science casework is 99% complete.
  • Ceilings are near complete.
Jr. High Wing & Office Area
  • Middle school wing has been punched out.
  • Punch-list items are being worked on.

Main Street
  • Painting of skylight framing is complete.
  • Drywall is complete.
  • Terrazzo is poured.
  • Display cases are being trimmed out.
Exterior
  • Access Road around school is complete.
  • North parking lot is complete.
  • South parking lot will be complete this week.
  • Sidewalks continue.
  • Electrical light pole bases are being installed.