Current Progress of New School

Gymnasium
Wood floor is near complete
Decals on the Gymnasium Floor
Independence Jr./Sr. High School gymnasium floor
Gymnasium

Weight/Wrestling Rooms
Painting has commenced and trim out is taking place.
Weight Room

Locker Rooms/FEMA Safe Room
  • Mechanical/Electrical/Plumbing rough in is complete.
  • Steel stud framing is complete.
  • EIFS and paint is near complete.
  • Tile is 90% complete on walls and floors at showers.
Locker Rooms/Safe Room

Music Rooms
Mechanical/electrical Trim out is near complete.
Band Room

Kitchen
Equipment installation is in progress.
Kitchen Storage Room

Auditorium
  • Concrete floors are complete.
  • Painting is 80% complete.
  • Drywall clouds are being hung.
  • Stage rigging is complete.
clouds in auditorium
Clouds in Auditorium
Stage Rigging

High School Wing
  • Painting is complete.
  • Grid is complete.
  • Doors and hardware are complete.
  • Toilet fixtures are complete.
  • Sills are installed.
  • Punch list in 1 ½ weeks.
Sr. High Classroom

Industrial Education Wing
  • Paint booth is installed.
  • Mechanical HVAC rough in continues.
Science, Art, Special Education, ETC
  • Terrazzo is ground
  • Mechanical/electrical trim out is in progress.
  • Science casework is near complete.
  • Ceiling grid is 90% complete.
  • Flooring has commenced.
Science Room

Middle School Wing & Office Area
  • Terrazzo is poured.
  • Ceiling grid is installed.
  • Painting is 90% complete.
  • Punch list in 3 ½ weeks.
Reception Desk

Main Street
  • Skylight is complete.
  • Drywall is 90% complete.
  • Terrazzo is poured but not ground.
  • Masonry is complete.
  • Tile is near complete at rest rooms.
Main Street

Display Case Area

Exterior
  • Concrete drive around building is 90% complete.
  • South Parking is 75% complete.
  • Sidewalks have commenced.
Access Road