| Gymnasium |
Wood floor is near complete
 |
| Decals on the Gymnasium Floor |
|
 |
| Gymnasium |
|
| Weight/Wrestling Rooms |
| Painting has commenced and trim out is taking place. |
 |
| Weight Room |
|
| Locker Rooms/FEMA Safe Room |
- Mechanical/Electrical/Plumbing rough in is complete.
- Steel stud framing is complete.
- EIFS and paint is near complete.
- Tile is 90% complete on walls and floors at showers.
|
 |
| Locker Rooms/Safe Room |
|
| Music Rooms |
| Mechanical/electrical Trim out is near complete. |
 |
| Band Room |
|
| Kitchen |
| Equipment installation is in progress. |
 |
| Kitchen Storage Room |
|
| Auditorium |
- Concrete floors are complete.
- Painting is 80% complete.
- Drywall clouds are being hung.
- Stage rigging is complete.
|
 |
| Clouds in Auditorium |
 |
| Stage Rigging |
|
| High School Wing |
- Painting is complete.
- Grid is complete.
- Doors and hardware are complete.
- Toilet fixtures are complete.
- Sills are installed.
- Punch list in 1 ½ weeks.
|
 |
| Sr. High Classroom |
|
| Industrial Education Wing |
- Paint booth is installed.
- Mechanical HVAC rough in continues.
|
|
| Science, Art, Special Education, ETC |
- Terrazzo is ground
- Mechanical/electrical trim out is in progress.
- Science casework is near complete.
- Ceiling grid is 90% complete.
- Flooring has commenced.
|
 |
| Science Room |
|
| Middle School Wing & Office Area |
- Terrazzo is poured.
- Ceiling grid is installed.
- Painting is 90% complete.
- Punch list in 3 ½ weeks.
|
 |
| Reception Desk |
|
| Main Street |
- Skylight is complete.
- Drywall is 90% complete.
- Terrazzo is poured but not ground.
- Masonry is complete.
- Tile is near complete at rest rooms.
|
 |
| Main Street |
|
|
 |
| Display Case Area |
|
|
| Exterior |
- Concrete drive around building is 90% complete.
- South Parking is 75% complete.
- Sidewalks have commenced.
|
 |
| Access Road |
|
No comments:
Post a Comment