Gymnasium |
- Gymnasium floor is finished.
- Bleacher install to start the week of June 24th
|
|
Weight/Wrestling Rooms |
- Painting is near complete.
- Ceiling grid is complete at weight room.
|
|
FEMA Safe Room |
- Mechanical/Electrical/Plumbing rough in is near complete.
- EIFS ceilings are complete in all shower areas.
- Walls are painted
- Cabinets are installed.
- Lockers are installed.
- Ceramic Tile is complete.
|
|
Music Rooms |
- Cabinet installation is near complete.
|
|
Kitchen |
- Existing equipment has been moved and installation is in progress.
|
|
Auditorium |
- Concrete floors, steps, and risers are complete.
- Painting is 80% complete.
- Drywall clouds are 100% framed and hung.
- Drywall clouds are 80% taped and finished.
- Rough in is complete.
- Speakers have been installed.
|
|
Sr. High School Wing |
- High School wing has been punched out.
- Punch-list items are being worked on.
|
|
Industrial Education Wing |
- Mechanical rough in is in progress.
- Auto and metal shop walls are primed
- Dust collection system in being installed
- Electrical rough in is in progress.
|
|
Science, Art, Special Education, ETC |
- Terrazzo is ground
- Mechanical/electrical trim out is in progress.
- Science casework is 99% complete.
- Ceilings are near complete.
|
|
Jr. High Wing & Office Area |
- Middle school wing has been punched out.
- Punch-list items are being worked on.
|
|
Main Street |
- Painting of skylight framing is complete.
- Drywall is complete.
- Terrazzo is poured.
- Display cases are being trimmed out.
|
|
Exterior |
- Access Road around school is complete.
- North parking lot is complete.
- South parking lot will be complete this week.
- Sidewalks continue.
- Electrical light pole bases are being installed.
|
|