Wednesday, July 17, 2013

July 2013 Construction Updates

Gymnasium
  • Bleacher install to be completed by July 26
Image
Weight/Wrestling Rooms
  • Painting complete
  • Ceramic tile is complete
  • Ceiling grid is complete
  • Weight room floor is in progress
Image
FEMA Safe Room
  • Mechanical/Electrical/Plumbing rough in is complete
  • Painting is complete
  • Lockers are installed
  • Fixtures are complete
  • Doors are being installed
  • Floors are sealed

Music Rooms
  • Areas are 99% complete and ready for inspection
Image
Kitchen
  • Existing equipment is complete and ready for inspection
Image
Auditorium
  • Painting is complete
  • Drywall clouds are complete
Sr. High School Wing
  • High School wing has been punched out.
  • Punch-list items are being worked on.
Industrial Education Wing
  • Painting is in progress
  • Auto and metal shop walls are primed
  • Dust collection system is being installed
Image
Science, Art, Special Education, ETC
  • Terrazzo is complete
  • Area has been punched out
  • Punch list items are being worked on
Image
Jr. High Wing & Office Area
  • Middle school wing has been punched out.
  • Punch-list items are being worked on.

Main Street
  • Painting is complete
  • Belbien wood is complete
  • Drywall is complete
  • Terrazzo is 50% complete
  • Remainder of Terrazzo will be ground by July 24
  • Display cases are being trimmed out
Image
Exterior
  • Access Road around school is complete
  • North parking lot is complete.
  • South parking lot is complete
  • Sidewalks are 90% complete
  • Electrical light pole bases are near complete
Image