Gymnasium |
- Bleacher install to be completed by July 26
|
Image
|
Weight/Wrestling Rooms |
- Painting complete
- Ceramic tile is complete
- Ceiling grid is complete
- Weight room floor is in progress
|
Image
|
FEMA Safe Room |
- Mechanical/Electrical/Plumbing rough in is complete
- Painting is complete
- Lockers are installed
- Fixtures are complete
- Doors are being installed
- Floors are sealed
|
|
Music Rooms |
- Areas are 99% complete and ready for inspection
|
Image
|
Kitchen |
- Existing equipment is complete and ready for inspection
|
Image
|
Auditorium |
- Painting is complete
- Drywall clouds are complete
|
|
Sr. High School Wing |
- High School wing has been punched out.
- Punch-list items are being worked on.
|
|
Industrial Education Wing |
- Painting is in progress
- Auto and metal shop walls are primed
- Dust collection system is being installed
|
Image
|
Science, Art, Special Education, ETC |
- Terrazzo is complete
- Area has been punched out
- Punch list items are being worked on
|
Image
|
Jr. High Wing & Office Area |
- Middle school wing has been punched out.
- Punch-list items are being worked on.
|
|
Main Street |
- Painting is complete
- Belbien wood is complete
- Drywall is complete
- Terrazzo is 50% complete
- Remainder of Terrazzo will be ground by July 24
- Display cases are being trimmed out
|
Image
|
Exterior |
- Access Road around school is complete
- North parking lot is complete.
- South parking lot is complete
- Sidewalks are 90% complete
- Electrical light pole bases are near complete
|
Image
|